T15 Fresh-food Phase 2 escalation call
2025-09-12·customer · Live-Services · 118 segments
Attendees: Lena Fischer, Sofia Almeida, Priya Nair, Marco Rossi
What this document established
Phase-2 escalation: six weeks behind (resourcing + negative-quantity defect), Sofia still ordering by hand and re-answering her 2024 explanation, go/no-go set for 15 November, DC-2 at reduced pace.
Conversation (turn by turn)
- turn 1 · 0:18 · 0:18 Marco Rossi 2025-09-12
And, i asked for this call because I would rather escalate early than explain later. Fresh-food Phase 2 is... about six weeks behind.
- turn 2 · 0:31 · 0:31 Lena Fischer 2025-09-12
Before you start, is shelf-life on
- turn 3 · 0:36 · 0:36 Sofia Almeida 2025-09-12
Mm.
- turn 4 · 0:37 · 0:37 Lena Fischer 2025-09-12
this agenda? Ana said it would be.
- turn 5 · 0:44 · 0:44 Marco Rossi 2025-09-12
Mm.
- turn 6 · 0:47 · 0:47 Marco Rossi 2025-09-12
It is, we will but... it. Ana put it on because email thread had thirteen messages in it and was going nowhere.
- turn 7 · 1:00 · 1:00 Priya Nair 2025-09-12
Yes.
- turn 8 · 1:03 · 1:03 Lena Fischer 2025-09-12
Six.
- turn 9 · 1:09 · 1:09 Priya Nair 2025-09-12
Right.
- turn 10 · 1:10 · 1:10 Marco Rossi 2025-09-12
Six. Two causes. The first is UAT resourcing on your side, we have not had the
- turn 11 · 1:25 · 1:25 Lena Fischer 2025-09-12
Mm, okay.
- turn 12 · 1:28 · 1:28 Marco Rossi 2025-09-12 · cited by uat-fresh-defect
people we planned for. The second is ours, there is a calculation defect in the fresh-food allocation module that produces negative quantities... in test.
- turn 13 · 1:47 · 1:47 Priya Nair 2025-09-12
Negative order quantities.
- turn 14 · 1:51 · 1:51 Marco Rossi 2025-09-12
Negative quantities,
- turn 15 · 1:56 · 1:56 Lena Fischer 2025-09-12
Yeah, yeah.
- turn 16 · 1:59 · 1:59 Marco Rossi 2025-09-12
yes. It is a boundary condition, it...
- turn 17 · 2:07 · 2:07 Lena Fischer 2025-09-12
Sure.
- turn 18 · 2:08 · 2:08 Marco Rossi 2025-09-12
is understood, it is not a mystery, but it has to be fixed before UAT means anything.
- turn 19 · 2:19 · 2:19 Lena Fischer 2025-09-12
How long to fix.
- turn 20 · 2:23 · 2:23 Marco Rossi 2025-09-12
Yeah.
- turn 21 · 2:26 · 2:26 Marco Rossi 2025-09-12 · cited by uat-fresh-defect
Days, not weeks. It is already in development.
- turn 22 · 2:34 · 2:34 Sofia Almeida 2025-09-12
Got it.
- turn 23 · 2:35 · 2:35 Lena Fischer 2025-09-12
And the UAT resourcing is mine.
- turn 24 · 2:39 · 2:39 Marco Rossi 2025-09-12
It is.
- turn 25 · 2:42 · 2:42 Lena Fischer 2025-09-12
Then I will fix that. Fresh is the top priority, Robert asks me about it every single time I see him, and... I am not going to be the reason it slips. I will add capacity.
- turn 26 · 3:06 · 3:06 Marco Rossi 2025-09-12
I mean Thank you.
- turn 27 · 3:13 · 3:13 Priya Nair 2025-09-12
Right.
- turn 28 · 3:15 · 3:15 Sofia Almeida 2025-09-12
Can I say something.
- turn 29 · 3:18 · 3:18 Lena Fischer 2025-09-12
Yes.
- turn 30 · 3:25 · 3:25 Priya Nair 2025-09-12
Yeah.
- turn 31 · 3:29 · 3:29 Sofia Almeida 2025-09-12
right I am still doing it by hand. That is what I want on the record. It is September twenty
- turn 32 · 3:44 · 3:44 Lena Fischer 2025-09-12
Yeah, yeah.
- turn 33 · 3:48 · 3:48 Sofia Almeida 2025-09-12
twenty-five and I am doing fresh ordering in a spreadsheet exactly the way I was doing it when I first met Marco.
- turn 34 · 3:59 · 3:59 Marco Rossi 2025-09-12
I know.
- turn 35 · 4:05 · 4:05 Sofia Almeida 2025-09-12
And your
- turn 36 · 4:10 · 4:10 Marco Rossi 2025-09-12
Mm.
- turn 37 · 4:11 · 4:11 Sofia Almeida 2025-09-12
consultant, the new one, Tomas's colleague, he sent me a questionnaire last into the...
- turn 38 · 4:20 · 4:20 Marco Rossi 2025-09-12
Mm-hm.
- turn 39 · 4:23 · 4:23 Sofia Almeida 2025-09-12
explain how...
- turn 40 · 4:29 · 4:29 Marco Rossi 2025-09-12
Mm, okay.
- turn 41 · 4:33 · 4:33 Sofia Almeida 2025-09-12
shelf life works in our categories.
- turn 42 · 4:36 · 4:36 Marco Rossi 2025-09-12
The questionnaire was Nadia's, and it was because the field mapping thread with Priya never resolved.
- turn 43 · 4:55 · 4:55 Sofia Almeida 2025-09-12
I am not on that thread.
- turn 44 · 4:59 · 4:59 Marco Rossi 2025-09-12
No, you are not.
- turn 45 · 5:02 · 5:02 Sofia Almeida 2025-09-12
Yeah, yeah.
- turn 46 · 5:05 · 5:05 Sofia Almeida 2025-09-12 · cited by story-repetition-cost,story-repetition-cost
So there has been a two month email conversation about my categories that I have
- turn 47 · 5:17 · 5:17 Marco Rossi 2025-09-12
Yes.
- turn 48 · 5:19 · 5:19 Sofia Almeida 2025-09-12
not been included in.
- turn 49 · 5:25 · 5:25 Marco Rossi 2025-09-12
Yes. Right.
- turn 50 · 5:33 · 5:33 Sofia Almeida 2025-09-12
True.
- turn 51 · 5:34 · 5:34 Sofia Almeida 2025-09-12 · cited by shl-recap-2025,shl-recap-2025,shl-recap-2025
But, i answered that question in March last last year. In the demo. It was the main thing I said. I said the shelf-life field is populated for about half the range and wrong for a portion of the rest, and that nothing in the ordering process knows whether something has three days left or three weeks. I remember saying it because it was the only reason I was in the room.
- turn 52 · 6:23 · 6:23 Marco Rossi 2025-09-12
You did say that.
- turn 53 · 6:28 · 6:28 Lena Fischer 2025-09-12
Of course.
- turn 54 · 6:32 · 6:32 Sofia Almeida 2025-09-12
So why am about the...
- turn 55 · 6:37 · 6:37 Priya Nair 2025-09-12
Mm-hm.
- turn 56 · 6:41 · 6:41 Sofia Almeida 2025-09-12
again eighteen months later.
- turn 57 · 6:48 · 6:48 Marco Rossi 2025-09-12 · cited by story-repetition-cost
Because the people who joined this project,
- turn 58 · 6:55 · 6:55 Sofia Almeida 2025-09-12
Right.
- turn 59 · 6:57 · 6:57 Marco Rossi 2025-09-12
did not have access to I mean... 1 second not make sure they did.
- turn 60 · 7:04 · 7:04 Priya Nair 2025-09-12
Yeah.
- turn 61 · 7:06 · 7:06 Sofia Almeida 2025-09-12
Okay so, i filled in the questionnaire anyway. It took me two hours.
- turn 62 · 7:16 · 7:16 Lena Fischer 2025-09-12
basically Sofia.
- turn 63 · 7:23 · 7:23 Sofia Almeida 2025-09-12 · cited by shl-recap-2025,story-repetition-cost
Yeah so, i am not being difficult, I am telling you the actual cost of this. Two hours of mine, and the answer worse than... the one I gave in March because I was rushing.
- turn 64 · 7:50 · 7:50 Marco Rossi 2025-09-12
That is a fair
- turn 65 · 7:53 · 7:53 Priya Nair 2025-09-12
Mm.
- turn 66 · 7:56 · 7:56 Marco Rossi 2025-09-12
criticism and I do not have a defence.
- turn 67 · 8:04 · 8:04 Priya Nair 2025-09-12
Agreed.
- turn 68 · 8:06 · 8:06 Priya Nair 2025-09-12
This has happened on our side too, yeah to be fair. The master data requirements were re-specified twice.
- turn 69 · 8:21 · 8:21 Sofia Almeida 2025-09-12
like And the threshold, the one that actually matters, is that anything under —
- turn 70 · 8:32 · 8:32 Lena Fischer 2025-09-12
yeah Sorry, Sofia, you have gone very quiet, are you still there?
- turn 71 · 8:41 · 8:41 Sofia Almeida 2025-09-12
Can you hear me?
- turn 72 · 8:45 · 8:45 Lena Fischer 2025-09-12
Mm.
- turn 73 · 8:46 · 8:46 Lena Fischer 2025-09-12
Now, kind of like yes.
- turn 74 · 8:50 · 8:50 Marco Rossi 2025-09-12
Mm, okay.
- turn 75 · 8:53 · 8:53 Marco Rossi 2025-09-12
Sorry Sofia, we lost about ten seconds.
- turn 76 · 9:00 · 9:00 Sofia Almeida 2025-09-12
Yeah.
- turn 77 · 9:02 · 9:02 Sofia Almeida 2025-09-12
It does not matter, it is in, the questionnaire.
- turn 78 · 9:15 · 9:15 Priya Nair 2025-09-12
Mm, okay.
- turn 79 · 9:19 · 9:19 Marco Rossi 2025-09-12
I mean
- turn 80 · 9:24 · 9:24 Priya Nair 2025-09-12
Mm-hm.
- turn 81 · 9:25 · 9:25 Marco Rossi 2025-09-12
Let me propose a way forward. First, we we fix the defect, and that that starts today. Second, I am and the... drive fresh-food UAT, at our cost, so the work does not sit waiting on your team having spare capacity.
- turn 82 · 9:55 · 9:55 Lena Fischer 2025-09-12
Sure.
- turn 83 · 9:57 · 9:57 Lena Fischer 2025-09-12
Two weeks is enough?
- turn 84 · 10:03 · 10:03 Marco Rossi 2025-09-12
Two weeks to get UAT moving properly. Third, I want to hold a fresh-food go or no-go decision on,
- turn 85 · 10:16 · 10:16 Lena Fischer 2025-09-12
Yeah, yeah.
- turn 86 · 10:19 · 10:19 Marco Rossi 2025-09-12
the fifteenth,
- turn 87 · 10:25 · 10:25 Sofia Almeida 2025-09-12
Right.
- turn 88 · 10:29 · 10:29 Marco Rossi 2025-09-12
of November. Not status update, from the...
- turn 89 · 10:36 · 10:36 Priya Nair 2025-09-12
Okay, yeah.
- turn 90 · 10:37 · 10:37 Lena Fischer 2025-09-12
November fifteenth.
- turn 91 · 10:40 · 10:40 Sofia Almeida 2025-09-12
Yeah, yeah.
- turn 92 · 10:43 · 10:43 Marco Rossi 2025-09-12
If we are not
- turn 93 · 10:48 · 10:48 Sofia Almeida 2025-09-12
Okay.
- turn 94 · 10:51 · 10:51 Marco Rossi 2025-09-12
One second. ready go live by so...
- turn 95 · 11:00 · 11:00 Priya Nair 2025-09-12
Mm.
- turn 96 · 11:03 · 11:03 Marco Rossi 2025-09-12
say so and we replan honestly rather than sliding.
- turn 97 · 11:12 · 11:12 Lena Fischer 2025-09-12
I would prefer that. And DC-2?
- turn 98 · 11:27 · 11:27 Sofia Almeida 2025-09-12
Yeah.
- turn 99 · 11:31 · 11:31 Marco Rossi 2025-09-12
The permanent fix is progressing but I am going be honest, it is progressing at reduced pace because the same engineers are on the defect.
- turn 100 · 11:46 · 11:46 Priya Nair 2025-09-12
Mm, okay.
- turn 101 · 11:48 · 11:48 Priya Nair 2025-09-12
like So DC-2 slips again.
- turn 102 · 11:57 · 11:57 Sofia Almeida 2025-09-12
Mm-hm.
- turn 103 · 11:58 · 11:58 Marco Rossi 2025-09-12 · cited by dc2-still-failing
DC-2 continues at reduced pace. I am when the...
- turn 104 · 12:03 · 12:03 Sofia Almeida 2025-09-12
Okay, yeah.
- turn 105 · 12:07 · 12:07 Marco Rossi 2025-09-12
to pretend it is going faster than it it is.
- turn 106 · 12:14 · 12:14 Priya Nair 2025-09-12
At least that is a straight answer.
- turn 107 · 12:19 · 12:19 Sofia Almeida 2025-09-12
Exactly.
- turn 108 · 12:21 · 12:21 Lena Fischer 2025-09-12
All right. Marco, yeah send me those four things in writing today, because I will need to walk Robert through,
- turn 109 · 12:35 · 12:35 Sofia Almeida 2025-09-12
Yeah.
- turn 110 · 12:37 · 12:37 Lena Fischer 2025-09-12
them tomorrow and he will ask for dates.
- turn 111 · 12:42 · 12:42 Marco Rossi 2025-09-12
Yeah.
- turn 112 · 12:46 · 12:46 Marco Rossi 2025-09-12
Today.
- turn 113 · 12:49 · 12:49 Lena Fischer 2025-09-12
Yeah.
- turn 114 · 12:52 · 12:52 Sofia Almeida 2025-09-12
And can whoever the consultant is read the, March notes before he talks to me.
- turn 115 · 13:04 · 13:04 Marco Rossi 2025-09-12
Mm-hm.
- turn 116 · 13:05 · 13:05 Marco Rossi 2025-09-12
He will read them before he talks to you.
- turn 117 · 13:10 · 13:10 Sofia Almeida 2025-09-12
Thank you.
- turn 118 · 13:17 · 13:17 Marco Rossi 2025-09-12
Yeah.