How to read this
Figures as measured in the 24 September 2024 master-data workshop (T06) and the remediation-scope email of 30 September 2024 (E13). Later movements (780 by late October, completion 19 December) are tracked separately — those are remediation progress, not the assessment.
What the archive establishes
The September 2024 master-data assessment found case-pack quantity missing on 31% of active articles.
Receipts (3)
- T06 3:31 · 2024-09-24 · Kwame Boateng
- T06 3:43 · 2024-09-24 · Priya Nair
- E13 message 1 of 6 · 2024-09-30 · Kwame Boateng
Priya Nair had predicted “about a third” before the measurement; the measured 31% matched her estimate.
Receipts (1)
- T06 3:43 · 2024-09-24 · Priya Nair
The same assessment found the store master and the product hierarchy clean.
Receipts (1)
- T06 3:50 · 2024-09-24 · Kwame Boateng
Supplier lead times were populated but distrusted: many were exactly seven days, the signature of a defaulted value rather than a measured one.
The first measured figure: shelf life was populated on 48% of the pilot-cohort articles — reported by Kwame Boateng in the 24 September 2024 master-data workshop and repeated in his 30 September remediation-scope email.
Still the last measured figure for the cohort as a whole. The 61% figure of December 2025 covers only the three fresh categories then in scope.
Receipts (2)
- T06 4:39 · 2024-09-24 · Kwame Boateng
- E13 message 1 of 6 · 2024-09-30 · Kwame Boateng
In December 2024 Ana Duarte recorded for the steering report that shelf life remained at 48% and untouched, and that it would become the critical path for phase two.
Receipts (1)
- E13 message 5 of 6 · 2024-12-20 · Ana Duarte
The remediation scope for the pilot cohort was 4,214 articles, of which 1,317 were missing case-pack quantity and 3,105 had missing or defaulted supplier lead times.
Receipts (1)
- E13 message 1 of 6 · 2024-09-30 · Kwame Boateng
After four weeks of remediation, 780 of the 1,317 case-pack values were done; two unresponsive suppliers accounted for about 200 articles.
Receipts (1)
- E13 message 2 of 6 · 2024-10-28 · Priya Nair
Case-pack remediation finished on 19 December 2024 — all 1,317 values. It took Priya’s team three weeks of overtime; for two unresponsive suppliers the case pack was inferred from six months of actual delivered quantities, which she recorded as “not ideal but it is right for 190 of the 200”.
Receipts (2)
- E13 message 4 of 6 · 2024-12-19 · Priya Nair
- T08 0:16 · 2025-01-21 · Priya Nair